Faster than planned: The server migration was completed in less than 20 hours

The planned JDS Management server migration has been successfully completed! 🎉

After the platform was taken fully offline on Friday, August 7, 2026, at around 6:30 PM, the migration was successfully completed on Saturday morning.

The entire server migration was therefore completed in less than 20 hours – significantly faster than the originally planned maintenance window until Monday morning.

All JDS Management apps are working again and JDS Management is fully accessible.


⚠️ Temporary longer loading times may occur

Following the successful migration, some users may temporarily experience longer loading times.

This is mainly caused by empty or newly rebuilt caches. Certain data needs to be loaded and cached again after the server migration.

This should improve automatically as the platform is used.

Longer loading times do not mean that the migration failed or that the platform is unavailable.


🕐 The Server Migration Timeline

The following times are rounded and partially estimated, as individual migration steps can overlap during an infrastructure change.

Friday, August 7, 2026

Approx. 4:30 PM – Domain introduced to the new server provider

The domain was initially connected to the new server environment.

Approx. 6:00 PM – Domain disconnected

The previous server environment was disconnected from the domain to prepare the actual migration.

Approx. 6:30 PM – JDS Management goes offline

JDS Management and its connected applications became temporarily unavailable.

Approx. 7:30 PM – Domain migration requested

The domain/DNS migration process was initiated.

Approx. 9:00 PM – Initial tests on the new server

The new server environment was tested extensively.


Saturday, August 8, 2026

Approx. 6:30 AM – DNS configured for the new server

The DNS configuration was updated to point the domain to the new infrastructure.

Approx. 6:45 AM – Latest JDS Management version deployed

The latest available JDS Management version was installed on the new server.

Approx. 7:00 AM – JDS Management accessible via HTTP

The platform became accessible again via HTTP.

Approx. 7:20 AM – SSL certificate created

A new SSL certificate was configured for secure HTTPS access.

Approx. 7:35 AM – SSL certificate online

Secure HTTPS access was successfully activated.

Approx. 8:00 AM – JDS Management and apps fully online

JDS Management was fully accessible again and the connected applications were operational.


🔐 New Infrastructure – Ready for the Future

The migration was more than just moving servers. The new infrastructure provides a stronger foundation for the continued development of JDS Management.

Our goals include:

  • 🚀 Better performance
  • 🔒 Improved data security
  • ⚡ Increased stability
  • 🔗 Better integration with new tools and services
  • 📈 More possibilities for future features
  • 🛠️ A more reliable technical foundation

JDS Management is now ready for its next development steps.


❤️ Thank You!

A server migration cannot simply be completed with one click.

We would therefore like to sincerely thank everyone who helped us during the migration, including everyone involved in testing and implementation.

And, of course, a huge thank you to all our customers and users.

Thank you for your patience and understanding during the temporary downtime!

With everyone's support and hard work, we were able to complete the entire server migration in less than 20 hours.


🎉 Welcome to the New Server!

The migration is complete.

JDS Management is online again, the apps are working, and the new infrastructure is ready for the future.

If you experience some longer loading times during the next few hours, please be patient while caches and temporary data are rebuilt after the migration.

Thank you for your trust!